TAKING OFF PROCESSES AND PREPARATION OF AN UN-PRICED BILL OF QUANTITIES
TAKING OFF PROCESSES AND PREPARATION OF AN UN-PRICED BILL OF QUANTITIES (A CASE STUDY OF THE PROPOSED FOUR (4) BEDROOM FULLY DETACHED DUPLEX AT PLOT 3003A AND 3003B SABONLUGBE EAST EXTENSION LAYOUT, CADASTRAL 07-07, ABUJA NIGERIA)
In partial fulfillment for the
requirement of the award of National Diploma (ND) in Quantity Surveying,
student will have to demonstrate what have been taught in class.
Thus,
this project which is a group work is aimed at taking off and preparing a
Un-Priced Bill of Quantities for the proposed Four (4) Bedroom Fully Detached
Duplex at plot 3003A and 3003B Sanbowlugbe East Extension Layout Cadastral Zone
07-07 Abuja Nigeria.
This
project is also aimed at exposing us to practical aspect of that which is not
taught in class and also enable us know more better about what has already been
taught in the class.
1.1 DESCRIPTION OF WORK
The project as it is
fully shown on the building drawing or plan is the construction of a proposed
four (4) Bedroom fully detached, duplex at 3003A and 3003B Sambowlugbe East
Extention layout cadastral Zone 07-07 Abuja, Nigeria.
For: Rainbow workstation service Ltd.
This
project work includes the process of taking off for the building, abstracting
and the process of preparing an un-priced bill of quantities for substructural
work only.
1.2 AIMS & OBJECTIVES
1.2.1
AIMS
The
aim of this project work is to prepared a taking off for quantities completely
for four (4) bedroom fully detached duplex and to prepare an abstract and
un-priced bill of quantities for the sub structural work.
1.2.2 OBJECTIVES
In order to achieve
the aforementioned aims, the following objectives are carried out.
-
To prepare literature review of some
terms for better understanding of the little of the project.
-
To prepare a taking off and squaring
quantities for four (4) bedrooms fully detached duplex.
-
To prepare an abstract for
substructure work only.
-
To prepare an un-priced bill of
quantities for substructure work only.
1.3 SCOPE AND LIMITATION
The
scope of this work is limited to the processes that are involved in taking off
and preparing an un-priced bill of quantities for building work but excluding
the abstracting, un-priced bill of quantities and service for super structural
work.
ABSTRACT
Class
work alone on measurement of building work is not enough to equipped the
student with the required knowledge and skill required on the measurement of
building work, it is against this background that the introduction of project
work was introduce to expose the student to practical and theoretical method of
taking off of building work apart from class work so as to increase their skill
and knowledge in addition to class work.
The
chapter one of this project demonstrate the aims and objectives of this
research, the scope and limitation while the chapter two and three represent a
literature review on measurement of building work in order to have a better
understanding of taking off, abstracting and billing processes prepared in
chapter for the proposed four (4) bedroom fully detached duplex.